Imperium

Dundas, ON
Imperium Banner_1440x625
Keywords: Climate Resilience, Enclosure, Passive House
  • Size 9-storey, 64-unit
  • Completion 2025
  • Services Provided Building Enclosure Consulting and Commissioning, Passive House Consulting, Airtightness Testing
  • Market Sector Residential
  • Architect DPAI
  • Owner Centurion (Dundas) Holdings Ltd. (RDH Client)
The purpose-built rental development combines Passive House Classic performance with a fully prefabricated concrete structure and enclosure. The project required the team to reconcile two distinct approaches in one building: Passive House enclosure performance and total-precast construction using insulated sandwich panels.

RDH led the Passive House and building enclosure work from early design through construction and certification, guiding the team through an accelerated detail development phase. The Design-Build team worked closely with Stubbe’s Precast in an early, design-assist-style process to develop repeatable details for panel-to-panel joints, factory-installed windows, balconies, roof and wall transitions, as well as foundation interfaces. This early collaboration helped translate Passive House requirements into practical fabrication and installation solutions while reducing technical and schedule risk.

Thermal bridging was a defining design challenge. RDH and Stubbe’s collaborated to develop new approaches for integrating balconies with the precast enclosure while maintaining insulation continuity and Passive House performance requirements. At the parking levels, where thermal bridges could be mitigated but not eliminated, RDH used whole-building energy modelling to understand the performance penalty and guide targeted improvements elsewhere in the enclosure so the project could remain within its energy budget.

Factory quality assurance was important in managing risk associated with the new enclosure system. RDH reviewed façade components and in-plant quality-control procedures at Stubbe’s facility and led mock-up air and water testing of panel joints and window installations. Findings could therefore be addressed before full production and repeated installation, helping limit site rework and support the accelerated erection sequence.

The completed building achieved Passive House Classic certification and a whole-building airtightness result of 0.59 ACH50. Its total-precast structure and enclosure were erected and made weathertight in approximately 12 weeks from the arrival of the first panels. The project demonstrates how early specialist involvement, performance modelling, enclosure testing, and close collaboration with the precast manufacturer can make a novel construction approach viable at Passive House performance levels.

Compressed_Imperium Carousel_1320x750
Imperium Carousel 2_1320x750
Imperium Carousel 3 Revised_1320x750

Technical Expertise. Real-World Impact.

Built on the best of building science. Subscribe for updates.

This field is for validation purposes and should be left unchanged.